Off-plan handover: snags in the handover report, 1 month to report missed visible defects, 5% balance can be held in escrow, action within 13 months.

In short

The livraison (handover) of a home bought off-plan is the handing over of the keys and the signing of a jointly drawn-up inspection report, the procès-verbal, in which you record your réserves (snags) (service-public.gouv.fr). Visible defects and non-conformities missed on the day can still be reported within one month of handover, by registered letter with acknowledgement of receipt (ANIL, the national housing information agency). The 5% balance of the price is due at handover, but it can be held in escrow if conformity is disputed (CCH, the Construction and Housing Code, art. R261-14). The developer cannot refuse to hand over the home on those grounds. To take legal action over visible defects, you have until the later of 1 year after the réception (formal acceptance) of the works and 13 months after taking possession (service-public.gouv.fr).

What handover means in law

Service-public.gouv.fr (sheet F2956, checked on 18 September 2026) defines handover as the buyer taking possession of the home, marked by the handing over of the keys and the signing of an état contradictoire (joint inspection report) between the developer and the buyer, which may contain snags.

The home must be complete. Under article R261-1 of the Code de la construction et de l’habitation (CCH, version in force since 1 September 2019), it is complete when “the works have been carried out and the items of equipment essential to its use have been installed”. Non-conformities that are not substantial and workmanship defects that do not make the works unfit for use do not prevent completion. They are not wiped out for all that: recording completion implies neither acceptance of conformity nor a waiver of your rights.

In practice, sheet F2956 cites water, gas, electricity and heating, as well as accessible common areas, with lifts and lighting in working order. “Minor imperfections” that do not prevent you from living there do not stop the handover.

Key handover day: the method

ANIL recommends that you:

  • inspect the home carefully;
  • check that the works conform to the plans and the contract;
  • test all the equipment;
  • “have a report drawn up in which any snags are recorded precisely”;
  • keep a dated and signed copy.

Writing a useful snag. A precise snag states the room, the item concerned and the defect observed. For the formal acceptance of works, service-public.gouv.fr warns that a visible defect not reported can no longer be claimed from the builder under the guarantees; only non-visible defects remain covered, depending on their nature (sheet F2958). Hence the value of being thorough.

The one-month window for missed visible defects

This is the least-known rule of VEFA (vente en l’état futur d’achèvement, off-plan sale). ANIL puts it this way: “The buyer has one month from handover to notify the seller, by registered letter with acknowledgement of receipt, of visible defects and non-conformities not mentioned at handover.”

This window lets you add to the report after a few weeks of living there: a window that does not close properly, a missing socket, a colour that differs from the specification. It is not a deadline for going to court but for notifying the seller.

The deadline for legal action. According to sheet F2956, action against the seller for visible defects “must be brought before the period expires (depending on the later event): either 1 year from formal acceptance, or 13 months from taking possession”. Where handover takes place after the formal acceptance of the works, the buyer has “one year from the end of the month following taking possession”. ANIL points out that you must go to court before this period expires if the repairs have not been made.

Holding the 5% balance in escrow

In a VEFA, calls for funds are capped at 95% of the price on completion of the building. The balance is payable when the premises are made available to the buyer; however, “it may be held in escrow if conformity with the terms of the contract is disputed” (CCH, art. R261-14, version in force since 1 September 2019).

In practice (service-public.gouv.fr, sheet F2956):

  • you do not pay the balance to the developer but deposit it with a third party, for example a notaire (notary) or the Caisse des dépôts et consignations (state deposit fund);
  • “the developer (seller) cannot refuse to hand over the home on the grounds that the balance is held in escrow”;
  • service-public.gouv.fr links to an online procedure for depositing the balance with the Caisse des dépôts et consignations (R65949).

ANIL specifies that the sum is then paid to the seller once the snags are cleared.

After handover: the guarantees that take over

Defects that appear after handover fall under the statutory guarantees, which run from the formal acceptance of the works (service-public.gouv.fr, sheet F2958, checked on 25 September 2026):

GuaranteeDurationWhat it covers
Parfait achèvement (completion)1 yearDefects recorded in the acceptance report or appearing within the year
Bon fonctionnement (proper working)2 yearsRemovable equipment, such as the hot-water cylinder
Décennale (ten-year)10 yearsDamage not detectable at acceptance, structural soundness, non-removable items

Sheet F2958 expressly lists the vendeur d’immeuble à construire (seller of a building to be constructed) among those liable.

FAQ

I found a defect three weeks after getting the keys: is it too late?

No, if it is a visible defect: you have one month from handover to notify the seller by registered letter with acknowledgement of receipt (ANIL).

The developer is demanding the balance before giving me the keys: is it entitled to?

The balance is due at handover, but it can be held in escrow if conformity is disputed (art. R261-14), and the developer cannot refuse handover on the grounds that the balance is held in escrow (service-public.gouv.fr).

How much can I hold in escrow?

The balance due at handover, i.e. at most 5% of the price, since payments cannot exceed 95% on completion (art. R261-14).

Until when can I go to court over a visible defect?

Until the later of these two dates: 1 year after the formal acceptance of the works, or 13 months after taking possession (service-public.gouv.fr, sheet F2956).

Do unfinished finishes prevent handover?

Not if they are minor imperfections that do not make the home uninhabitable (sheet F2956; art. R261-1). Record them as snags.

Which professional to consult

A diagnostiqueur (property surveyor) or a géomètre-expert (chartered surveyor) can accompany you at handover to check floor areas and spot defects to record as snags. The notaire (notary) can receive the balance held in escrow. On completion guarantees before handover, see our guide garantie financière d’achèvement (financial completion guarantee); on delays, retard de livraison en VEFA (late handover of an off-plan home).

Find a professional

One professional per trade and per area, selected and scored out of 100 from public data, with a verifiable title. The trade, its official register and the professionals selected (pages in French):

The property surveyor (diagnostics) selected in the largest cities

CityProfessionalAreaScore /100Status
ParisExpertise & DiagnosticParis, 15e arrondissement79Selected
MarseilleADK Diag 13Marseille, 1er arrondissement87Selected
ToulouseMCP Diagnostic & IngénierieToulouse90Selected
NiceNiceDiagnosticNice74Selected
LyonQualitech Expertises ImmobilièresLyon, 3e arrondissement82Selected
MontpellierDIMO DiagnosticMontpellier82Selected
BordeauxAquitaine Diagnostic ImmobilierBordeaux74Selected
LilleJBM ExpertiseLille78Selected
RennesSHD DiagnosticsRennes70Selected
ToulonDIADEXToulon81Selected

The 10 cities with the most sales (DVF 2025) where a property surveyor (diagnostics) is selected; in a city with several areas, the best-scoring profile. "Verified": title read at the register by Payotte; "Selected": title declared, verifiable on the profile.

Related guides

Sources

All guides on buying in France · Prices and professionals, city by city