In short
The delivery deadline is a compulsory particular of the deed of sale in a VEFA (vente en l’état futur d’achèvement, off-plan sale) (code de la construction et de l’habitation, CCH, art. L261-11). The contract almost always provides for legitimate grounds for postponement: bad weather, strikes, a contractor’s bankruptcy, force majeure (service-public.gouv.fr; ANIL). Outside these cases, the seller must in principle pay the late-delivery penalties provided for in the contract (service-public.gouv.fr, sheet F2956). You can also refuse to pay the balance, apply for rescission (résolution) of the sale if the delay is serious, or claim damages: rehousing, furniture storage, interim loan interest, lost rent. Conversely, if you are the one paying late, the contractual penalty cannot exceed 1% per month (CCH, art. R261-14).
The delivery deadline, a compulsory particular
Article L261-11 of the code de la construction et de l’habitation (CCH, Construction and Housing Code, version in force since 25 November 2018) requires the VEFA contract, concluded by acte authentique (deed executed before a notary), to specify in particular the delivery deadline. Service-public.gouv.fr (sheet F2961, checked on 18 September 2026) also lists any late-delivery penalties among the clauses of the deed.
A point of caution raised by ANIL: the delivery deadline is often expressed loosely, and “legitimate grounds for suspending the deadline are very generally provided for in [the] contract of sale: bad weather, general strike…”. Read this clause in the draft deed, which you receive before signing.
Compare with a detached house. Under a contrat de construction de maison individuelle (CCMI, house building contract), late-delivery penalties are compulsory and cannot be less than 1/3,000 of the agreed price per day of delay (CCH, art. R231-14). No equivalent rule appears in the sources read for the VEFA: sheet F2956 refers to the penalties “provided for” in the contract. See our guide CCMI (house building contract).
Legitimate grounds for postponement
Sheet F2956 cites, as grounds commonly stipulated in the “clauses de retard légitime” (legitimate delay clauses):
- bad weather: “days of frost, snow, heavy rain or strong wind making the site dangerous or technically impossible”;
- strikes;
- a contractor’s bankruptcy;
- force majeure.
Force majeure has a legal definition. It is “an event beyond the debtor’s control, which could not reasonably have been foreseen when the contract was concluded and whose effects cannot be avoided by appropriate measures”, which prevents performance (code civil, the Civil Code, art. 1218).
The postponement only applies within the limits of the clause: a delay that exceeds the justified days is still a delay.
Your remedies for an unjustified delay
The Civil Code (art. 1217, version in force since 1 October 2018) offers five responses to non-performance of a contract: refusing to perform or suspending your own obligation, seeking enforced performance, obtaining a price reduction, bringing about rescission of the contract, claiming compensation. Service-public.gouv.fr (sheet F2956) applies them to the VEFA:
1. Refusing to pay the balance (exception d’inexécution, defence of non-performance). You can “refuse to pay the balance of the price as long as the seller has not performed its obligation”. A warning: if the contract contains a clause résolutoire (termination clause), the seller can serve you with a commandement de payer (formal demand for payment), and you then have one month to settle or apply to the court.
2. Claiming the penalties. “If delivery is late in relation to the contractual date, the seller must, in principle, pay the late-delivery penalties provided for”. They require a clause pénale (penalty clause) in the contract and an unjustified delay.
3. Applying for rescission. You can “apply for rescission of the sale, that is, cancellation of the contract, where the delay is sufficiently serious”, by agreement or by court decision.
4. Claiming damages, “independently or in addition”. The sheet cites: rehousing costs, loss of the chance to receive rent, furniture storage costs, intérêts intercalaires (interim interest) on the mortgage, unnecessary insurance premiums, as well as non-financial loss (préjudice moral).
The competent court depends on the amount: the tribunal de proximité (local court) up to €10,000, the tribunal judiciaire (civil court) above that (sheet F2956).
If the developer never finishes
A delay can be a sign of failure. In that case, the garantie financière d’achèvement (financial completion guarantee) pays for the end of the works, or the refund guarantee returns the sums paid if the sale is cancelled (service-public.gouv.fr, sheet F39743). The seller must have taken it out before signing (CCH, art. L261-10-1). See our guide garantie financière d’achèvement (completion guarantee).
And if the buyer pays late?
Calls for funds are capped (35% at foundations, 70% when the building is weathertight, 95% on completion). If the contract provides for a penalty for late payment, its rate “may not exceed 1% per month” (CCH, art. R261-14, version in force since 1 September 2019).
FAQ
The developer claims 40 days of bad weather: do I have to accept it?
Only within the limits of the legitimate delay clause in your contract. Sheet F2956 refers to days of frost, snow, heavy rain or strong wind making the site dangerous or technically impossible. Ask for a breakdown of the days counted.
Are late-delivery penalties automatic in a VEFA?
They are due “in principle” if the contract provides for them and if the delay is not justified (service-public.gouv.fr). Their amount is the one in the contract; the floor of 1/3,000 per day is specific to the CCMI (art. R231-14).
Can I withhold payment of the balance?
Yes, through the defence of non-performance, as long as the seller has not delivered. Beware of the termination clause: after a formal demand for payment, you have one month to settle or apply to the court (sheet F2956).
What costs can I get reimbursed?
Rehousing, furniture storage, interim interest on the loan, unnecessary insurance, lost rent if the property was to be let, and non-financial loss, to be proven before the court (sheet F2956).
Can a delay justify cancelling the sale?
Yes, if it is sufficiently serious: rescission can be obtained by agreement or by court decision (sheet F2956; Civil Code, art. 1217).
Which professional to consult
The notaire (notary) who executed the deed can tell you the exact deadline clause, grounds for postponement and penalty clause. If the delay forces you to extend a bridging loan or bear interim interest, the courtier en crédit (mortgage broker) works out the extra cost, which is useful for your damages claim. At handover, see our guide livraison en VEFA et réserves (off-plan handover and snagging).
Find a professional
One professional per trade and per area, selected and scored out of 100 from public data, with a verifiable title. The trade, its official register and the professionals selected (pages in French):
The notary selected in the largest cities
| City | Professional | Area | Score /100 | Status |
|---|---|---|---|---|
| Paris | Dextera Notaires | Paris, 7e arrondissement | 91 | Selected |
| Marseille | 1391 Notaires | Marseille, 8e arrondissement | 85 | Selected |
| Lyon | Archers Notaires | Lyon, 2e arrondissement | 92 | Selected |
| Montpellier | Lexnot | Montpellier | 93 | Selected |
| Bordeaux | 1645 Notaires | Bordeaux | 90 | Selected |
| Lille | Notaires Lille Royale | Lille | 70 | Selected |
| Rennes | Notaires des Lices | Rennes | 87 | Selected |
| Dijon | Legatis Dijon-Genlis | Dijon | 86 | Selected |
| Brest | Quid Novi Brest Notaires & Conseils | Brest | 86 | Selected |
| Cannes | 1795 | Cannes | 70 | Selected |
The 10 cities with the most sales (DVF 2025) where a notary is selected; in a city with several areas, the best-scoring profile. "Verified": title read at the register by Payotte; "Selected": title declared, verifiable on the profile.
Related guides
Sources
- Livraison d'un logement vendu en état futur d'achèvement (Vefa) (service-public.gouv.fr, vérifié le 18 septembre 2026) (checked 11 October 2026)
- Acte de vente d'un logement en l'état futur d'achèvement (Vefa) (service-public.gouv.fr, vérifié le 18 septembre 2026) (checked 11 October 2026)
- Vente en l'état futur d'achèvement (Vefa) (service-public.gouv.fr, vérifié le 18 septembre 2026) (checked 11 October 2026)
- Code civil, articles 1217 et 1218 (Légifrance) (checked 11 October 2026)
- Code de la construction et de l'habitation, articles L261-1 à L261-22 (Légifrance) (checked 11 October 2026)
- Code de la construction et de l'habitation, articles R261-11 à R261-16 (Légifrance) (checked 11 October 2026)
- Code de la construction et de l'habitation, articles R231-1 à R231-14 (Légifrance) (checked 11 October 2026)
- Acheter sur plan (ANIL) (checked 11 October 2026)