RERA complaint for a delayed flat: refund or delay interest

Section 18 of RERA: refund with interest or interest for every month of delay, how to file a complaint with the state authority, and how appeals work.

In short

If a builder does not hand over a flat by the date in the agreement for sale, section 18 of the Real Estate (Regulation and Development) Act, 2016 gives the buyer (the “allottee”) two choices: withdraw and get the whole amount back with interest, or stay in the project and be paid interest for every month of delay until possession. The rate is not in the Act: each state prescribes it in its rules. In Haryana, it is the State Bank of India’s highest marginal cost of lending rate (MCLR) plus 2% (rule 15, as applied by the Haryana authority and tribunal). You complain to the RERA authority of the state where the project is (s. 31), and appeal to the state’s Appellate Tribunal within 60 days (s. 44).

The rule

  • Who can claim: an allottee whose promoter fails to complete or give possession “in accordance with the terms of the agreement for sale or … by the date specified therein”, or because its registration was suspended or revoked (s. 18(1)).
  • Option 1, withdraw: the promoter must “return the amount received … with interest at such rate as may be prescribed in this behalf including compensation” (s. 18(1)).
  • Option 2, stay: “where an allottee does not intend to withdraw from the project, he shall be paid, by the promoter, interest for every month of delay, till the handing over of the possession” (proviso to s. 18(1)).
  • Same rate both ways: the rate the promoter charges a buyer who pays late must equal the rate the promoter pays when it defaults, and the promoter’s interest runs “from the date the promoter received the amount” until it is refunded (Explanation to s. 2(za)).
  • Without prejudice: the refund right applies “without prejudice to any other remedy available” (s. 18(1)). The Supreme Court called it “unqualified” in Imperia Structures Ltd. v. Anil Patni, paragraph 25, quoted in its order of 28 March 2022 in Civil Appeal No. 1816 of 2022.

Who decides what

The Act has two decision-makers inside each state authority:

ClaimDecided bySource
Refund with interest, or interest for delayThe AuthorityNewtech Promoters and Developers v. State of U.P. (2021), paragraph 86, as quoted by the Haryana authority, Gurugram
Compensation for loss (sections 12, 14, 18 and 19)The adjudicating officer, a person who is or was a District Judges. 71(1)

In paragraph 86 of Newtech, the Supreme Court said that for refund, interest on the refund or interest for delayed possession, “it is the regulatory authority which has the power to examine and determine”, while compensation and interest on it belong to the adjudicating officer. Compensation takes account of the builder’s unfair gain, the buyer’s loss and repeated default (s. 72).

The interest rate, state by state

The Act leaves the rate to the state rules. What Payotte read:

StateRate for refund and delay interestSource
HaryanaSBI highest MCLR + 2% (rule 15). In an order of 30 May 2023 the authority applied 10.70% (8.70% + 2%)Haryana Real Estate Appellate Tribunal, Appeal No. 517 of 2023
Uttar PradeshNot readable: in the English translation published by UP-RERA, the heading of rule 15 (“Rate of interest payable by the promoter and the allottee”) is followed by text on website back-ups, not by a rateUP rules, chapter V

Other states set their own rate. Because the reference rate moves, the percentage depends on the date of the order. The tribunal in Appeal No. 517 of 2023 refused a higher contractual rate, holding that “provisions of law would override any agreement”.

Calculation, not a quote: ₹40,00,000 paid and a rate of 10.70% a year give about ₹4,28,000 of interest per year of delay, or about ₹35,700 per month. Interest on a refund runs from each payment date.

Step by step

  1. Check the dates in your agreement and on the RERA project page. See how to check a RERA project registration.
  2. Choose your remedy. Refund (withdraw) or delay interest (stay). The Supreme Court put it as “it is up to the allottee to proceed either under Section 18(1) or under proviso to Section 18(1)” (Imperia, paragraph 25).
  3. Write to the promoter. Section 18 makes the promoter liable “on demand”. Keep a dated copy.
  4. File the complaint with the state authority (s. 31). The form, manner and fee are set by each state. In Uttar Pradesh, a complaint to the Authority is filed on Form M and a claim for compensation to the adjudicating officer on Form N, each with a fee of ₹1,000 (UP rules 33 and 34). The UP-RERA manual describes online filing in its eCourts module, payment of the ₹1,000 through the SBI gateway, and a signed physical copy once the complaint has been cleared.
  5. Attach the evidence: agreement, receipts, bank statements, correspondence.
  6. Hearing. The authority must dispose of matters within 60 days or record why it did not (s. 29(4)); the adjudicating officer has the same target (s. 71(2)).
  7. Enforcement. Interest, penalty or compensation that is not paid is “recoverable … as an arrears of land revenue” (s. 40(1)). Under the UP rules a refund with interest is payable within 45 days of becoming due (rule 16).

Appeals

  • To the Appellate Tribunal of the state, within 60 days of receiving the order; late appeals are allowed for “sufficient cause” (s. 44(2)). In Uttar Pradesh the appeal fee is ₹1,000, on Form L (rule 25).
  • Builder’s pre-deposit: a promoter’s appeal is not heard until it deposits at least 30% of the penalty, or the total amount payable to the allottee with interest and compensation (proviso to s. 43(5)).
  • To the High Court, within 60 days of the tribunal’s order, on the grounds in section 100 of the Code of Civil Procedure (s. 58).
  • Civil courts are barred from matters the Authority, the adjudicating officer or the Tribunal can decide (s. 79). Consumer commissions are a separate route: see consumer commission complaints by homebuyers.

Which professional to consult

A property lawyer (advocate) enrolled with the State Bar Council can draft the complaint and compute the interest from each payment date. This guide is general information, not legal advice. See property lawyers.

Frequently asked questions

Can I get both a refund and delay interest?

Not for the same period. You either withdraw and get the refund with interest, or stay and get interest for every month of delay until possession (s. 18(1) and its proviso).

Is the rate the one in my agreement?

The Act refers to the rate “prescribed” in the state rules, and makes it the same for both sides (s. 2(za)). In Haryana the tribunal rejected a contractual rate in favour of the rule’s rate.

Can I claim compensation for mental harassment?

Compensation is decided by the adjudicating officer under sections 71 and 72, not by the Authority. File the claim before the officer.

Can I complain to a consumer commission instead?

The UP-RERA FAQ says consumer forums “have not been barred” by the Act, and that the same dispute cannot be pursued before both. See the consumer commission guide.

Sources and limits

The Haryana rate is read in Haryana orders quoting rule 15, not in the rules themselves; Newtech is quoted from a Haryana order, the Supreme Court text being unreachable. The UP rate could not be read.